Progress Day care centre

Dear sponsors,

Finally the festivals came to an end! What happened in the last 2 months?
The most important day was on the 5th of October when they put the “DALAN”. This is putting cement on the first floor, so the ground floor gets a ceiling.
A lot of workers came to do this job. Everything is supported with bamboo.

Meanwhile also the Tihar festivities ended and now we have the problem that nobody wants to come to work! The government gave out a message that they will give money to people who want to put up their own business. But you’ll have to apply and make a full report of what you want to do. Most people gave up their work and just sit around waiting!!!

In the second half of October, they started to make also the pillars on the first floor. It is getting winter and so much colder on the mountain Sarangkot. We try to plaster the down rooms and make them ready for the little children.

Thank you so much for your support!

Sabine & Ram Chandra Sharma

Iron gridIron grid

Passing cement by handPassing cement by hand

Levelling the cementLevelling the cement

Cement machineCement machine

Passing cement from down to upPassing cement from down to up

Frontside + pillars first floorFrontside + pillars first floor

BacksideBackside